West London, UK (Victoria Road to Green Park Way) · 2024-2025 (Launched February 2024, completed June 2025) · £87.7bn - £102.7bn (HS2 project total, 2025 prices)

The judgement call

Account action unavailable

TBM Emily was the third of four TBMs for the Northolt Tunnel. Named after Emily Brontë. It completed its 3.4-mile drive under London.

Key engineering challenges

Tunnelling under densely populated urban areas. - Managing ground movements and settlement.

Project facts

Client / owner
HS2 Ltd.
Lead contractor
SCS JV (Skanska Costain STRABAG Joint Venture)
Lead designers
Project type
new build
Scale
Tunnel length: 13.5 km (8.4 miles) twin-bore tunnel; Drive length: 5.5 km (3.4 miles); TBM diameter: 9.11m
Disciplines
civil; structural; mechanical; electrical; systems; tunnelling; geotechnical
Standards & frameworks
UK railway standards, CDM Regulations (implied).

Sources: HS2.org.uk (https://www.hs2.org.uk/building-hs2/tunnels/twin-bore-tunnels/northolt-tunnel/) - New Civil Engineer (https://www.newcivilengineer.com/latest/hs2-third-london-tbm-extracted-from-ground-29-07-2025/) - LinkedIn (https://www.linkedin.com/posts/british-tunnelling-society_third-hs2-tbm-completes-drive-beneath-london-activity-7338851721093242880-kZ7O)