Flamanville, France [INTERNATIONAL] · Construction 2007-2024, Operations began 2024 · ~£20.4bn (2020 prices, based on €23.7bn and ~0.86 GBP/EUR)

The judgement call

Account-gated at launch

The project faced numerous technical challenges and delays, leading to substantial cost increases from an initial estimate of €3.3 billion to €13.2 billion (and later €23.7 billion). - Lessons learned regarding the need for robust project management, supply chain oversight, and early identification of technical issues in complex nuclear new build projects. - The experience has influenced the design and construction strategies for other EPR projects, including Hinkley Point C.

Key engineering challenges

Significant cost overruns and delays, highlighting the complexities of building Generation III+ reactors. - Technical issues with critical components, such as the reactor pressure vessel and steam generators. - Managing a large and diverse international workforce and supply chain. - Ensuring stringent safety and regulatory compliance throughout construction and commissioning.

Project facts

Client / owner
EDF (Electricité de France)
Lead contractor
EDF, Framatome
Lead designers
Areva, Siemens (EPR design)
Project type
new build
Scale
1650 MWe (EPR reactor)
Disciplines
nuclear; civil; structural; mechanical; electrical; process; safety
Standards & frameworks
ASN (French Nuclear Safety Authority) regulations

Sources: World Nuclear News: France’s Flamanville EPR starts supplying power (https://www.world-nuclear-news.org/articles/french-epr-starts-supplying-power) - World Nuclear Association: Flamanville 3 (https://world-nuclear.org/nuclear-reactor-database/details/flamanville-3) - ANS Nuclear News: Flamanville-3 reaches full power (https://www.ans.org/news/article-7625/flamanville3-reaches-full-power/) - ITIF: Lessons From France’s Nuclear Program (https://itif.org/publications/2025/09/02/lessons-from-frances-nuclear-program/) - Reddit: France’s new Nuclear power plant Flamanville EPR costed (https://www.reddit.com/r/europe/comments/1i2qy3f/frances_new_nuclear_power_plant_flamanville_epr/) - Assystem: Construction and commissioning activities for the (https://www.assystem.com/en/references/configuration-construction-commissioning-activities-flamanville-3/)